Nearly 5,000 windows replaced across 345 occupied homes, with asbestos abatement mid-scope.

Project Overview

MTCC 702 engaged EBS to address persistent thermal and moisture issues across their 345-unit upscale Toronto townhouse community, replacing nearly 5,000 windows and sliding doors. Every unit was occupied throughout, making resident coordination and minimal disruption non-negotiable from the start. Mid-project, asbestos was discovered in the window surrounds. A complication that required immediate abatement before work could continue. Abatement was completed and drywall reinstatement followed in record turnaround times, without derailing the overall program schedule. The scale alone, 345 properties, thousands of individual openings, demanded an organizational system built specifically for this project. It is exactly the kind of program where proactive risk management determines whether a project holds together or falls apart.

Execution Strategy

At this scale, construction management is fundamentally a logistics problem. Scheduling across 345 individual properties required a sequencing approach that balanced crew efficiency with resident access and occupancy. When asbestos was identified in the window surrounds, the response had to be immediate, compliant, and fast. Abatement protocols were activated without disrupting the broader program timeline. Drywall reinstatement after abatement was executed in tight turnaround windows to restore each home quickly. Resident communication was a continuous workstream throughout, keeping occupants informed and maintaining trust across a large, active community. The certainty this kind of project demands is built before the first window comes out, in the planning.

No items found.
Project Details
icon
Location:
Toronto, ON
icon
Status:
Completed
icon
Size:
345 Properties ~5,000 Windows & Sliding Doors
Our Work

Proof Is in the Spaces We've Built

A 56,000 sq. ft. wealth management headquarters built for quiet authority.

A federal agency workspace delivered on time and on budget during the pandemic.

Five floors of bold, branded workspace built for a company on the move.

icon
icon
Certainty is the Only
Explore all projects
Standard We Know.